Celonic expands its office space in Germany with a new administration building by summer 2020

Celonic Group is gearing up for an expansion of its Heidelberg site real estate with an approximately 2000 square meter building that adds more than 100 work spaces including offices and labs.

This would almost double the number of employees at Celonic’s largest GMP-manufacturing site and would be mainly used for administrative and management department at the superior floors. Labs for Quality Control department would be in the ground floor.

According to the current disclosed plan, the building application should be sent by the end of January 2019. The implementation is to be carried out in two phases: cut of spade by June 2019 followed by the completion of the building structure by January 2020. The fully equipped offices and labs will most probably be ready for occupancy starting with summer 2020.